A subcontractor submits product data too late for coordination. Under AIA A401, what duty is implicated?

Correct Answer

C) Submit required shop drawings and product data with reasonable promptness and proper sequence

A401 requires subcontractor submittals with reasonable promptness and sequencing to avoid delay.

Answer Options
A
Submit product data only after final payment, when coordination problems cannot be corrected
B
Avoid submittals because subcontractors never provide them
C
Submit required shop drawings and product data with reasonable promptness and proper sequence
D
Replace the building permit process with a product-data stamp

Why This Is the Correct Answer

A401 requires subcontractor submittals with reasonable promptness and sequencing to avoid delay.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.