Welding is planned above combustible finishes in an occupied area. What controls should be in place?
Correct Answer
B) Use hot-work controls
Hot work requires appropriate permits, fire watch, and protection controls.
Why This Is the Correct Answer
Hot work requires appropriate permits, fire watch, and protection controls.
Why the Other Options Are Wrong
Option A: Finish quickly and skip documentation
Finish quickly and skip documentation may relate to another site control, but it does not remove or guard the hot work exposure being tested.
Option C: Use the weather report as fire-watch proof
Use the weather report as fire-watch proof may relate to another site control, but it does not remove or guard the hot work exposure being tested.
Option D: Treat owner awareness as the permit
Treat owner awareness as the permit may relate to another site control, but it does not remove or guard the hot work exposure being tested.
Memory Technique
Hazard lock for Coordinates Welding: hot is the harm, appropriate is the guard.
Reference Hint
Open-book path: tab OSHA 29 CFR 1926; Contractor's Manual to Hot work and fire prevention controls; verify the quantity, Florida notice/permit rule, or field-control record before answering.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A proposed subcontractor offers to perform regulated structural work but cannot show a current Florida contractor credential for that work. What is the licensing risk?
Next Question
A pad requires 3,250 cy of compacted fill. Borrow material yields 88% after placement and compaction. How many loose cubic yards should be ordered?