A proposed subcontractor offers to perform regulated structural work but cannot show a current Florida contractor credential for that work. What is the licensing risk?
Correct Answer
B) Unlicensed contracting can trigger enforcement action, including stop-work consequences
Florida licensing law prohibits unlicensed contracting and authorizes enforcement for covered work.
Why This Is the Correct Answer
Florida licensing law prohibits unlicensed contracting and authorizes enforcement for covered work.
Why the Other Options Are Wrong
Option A: The subcontractor may perform the work if its material supplier has a business tax receipt
The subcontractor may perform the work if its material supplier has a business tax receipt relies on the wrong note, symbol, sheet, scale, or detail path for unlicensed contracting.
Option C: The missing credential is cured by adding a larger contingency to the estimate
The missing credential is cured by adding a larger contingency to the estimate relies on the wrong note, symbol, sheet, scale, or detail path for unlicensed contracting.
Option D: The permit card automatically licenses every subcontractor listed in the bid log
The permit card automatically licenses every subcontractor listed in the bid log relies on the wrong note, symbol, sheet, scale, or detail path for unlicensed contracting.
Memory Technique
Screens Structural is an address; follow it to the real instruction.
Reference Hint
Open-book path: tab Florida Statutes Chapter 489 to Section 489.127 prohibitions and penalties; confirm the required quantity, authority, timing, or record before selecting the answer.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
