Contract AdminProceduresmedium13% of exam part

A sleeve location conflict will affect tomorrow's concrete pour. What should the PM do?

Correct Answer

A) Use RFI control

Field conflicts affecting work should follow controlled RFI or clarification procedures.

Answer Options
A
Use RFI control
B
Pour first and ask later
C
Let the concrete supplier choose the location
D
Move the issue to the warranty log

Why This Is the Correct Answer

Field conflicts affecting work should follow controlled RFI or clarification procedures.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.