EstatePass
Contract AdminProceduresmedium13% of exam part

A submittal is marked rejected, but material is already staged for installation. What should the GC do?

Correct Answer

B) Hold installation and obtain an acceptable resubmittal

Rejected submittals are not a release for installation.

Answer Options
A
Install it because delivery means acceptance
B
Hold installation and obtain an acceptable resubmittal
C
Use the delivery ticket as the architect's approval
D
Close the submittal log without distributing comments

Why This Is the Correct Answer

Rejected submittals are not a release for installation.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.