EstatePass
Contract AdminPreconstructionmedium27% of exam part

An addendum adds 260 lf of handrail at $142 per lf installed. What amount should be added to the bid?

Correct Answer

D) $36,920

Multiply added quantity by installed unit price.

Answer Options
A
$34,060
B
$38,480
C
$40,820
D
$36,920

Why This Is the Correct Answer

Multiply added quantity by installed unit price.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.