A footing pour is scheduled, but required reinforcing inspection has not passed. What should the superintendent do?
Correct Answer
D) Hold the pour until required inspection approval
FBC Chapter 1 requires required inspections before work is covered or proceeds past inspection points.
Why This Is the Correct Answer
FBC Chapter 1 requires required inspections before work is covered or proceeds past inspection points.
Why the Other Options Are Wrong
Option A: Pour and ask the inspector to approve from photos later
Pour and ask the inspector to approve from photos later relies on the wrong note, symbol, sheet, scale, or detail path for inspection readiness.
Option B: Use the concrete ticket as the inspection approval
Use the concrete ticket as the inspection approval relies on the wrong note, symbol, sheet, scale, or detail path for inspection readiness.
Option C: Move reinforcing inspection to the warranty period
Move reinforcing inspection to the warranty period relies on the wrong note, symbol, sheet, scale, or detail path for inspection readiness.
Memory Technique
Foundation Crew is an address; follow it to the real instruction.
Reference Hint
Open-book path: tab Florida Building Code, Building, 8th Edition (2023), Chapter 1 Administration to Chapter 1 Section 110 inspections; verify the quantity, approval point, notice rule, or field record before answering.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
