Contract AdminPermitsmedium20% of exam part

The recorded notice of commencement omits the lender information even though a lender exists. Which chapter should the PM review?

Correct Answer

B) Chapter 713 notice-of-commencement information requirements

Chapter 713 sets required information for the notice of commencement.

Answer Options
A
Chapter 489 worker productivity rates
B
Chapter 713 notice-of-commencement information requirements
C
AIA A401 subcontract payment timing only
D
The contractor's daily weather report form

Why This Is the Correct Answer

Chapter 713 sets required information for the notice of commencement.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.