A Dania Beach logistics plan adds 6 off-hour deliveries at $425 each. What added logistics cost should be forecast?

Correct Answer

D) $2,550

Added logistics cost equals delivery count multiplied by cost per delivery.

Answer Options
A
$431
B
$2,125
C
$3,550
D
$2,550

Why This Is the Correct Answer

Added logistics cost equals delivery count multiplied by cost per delivery.

Why the Other Options Are Wrong

Option A: $431

$431 is below the supported result for jobsite logistics cost; it likely skips a premium-pay or employer-cost component.

Option B: $2,125

$2,125 is below the supported result for jobsite logistics cost; it likely skips a premium-pay or employer-cost component.

Option C: $3,550

$3,550 is above the supported result for jobsite logistics cost; it likely pays the wrong premium tier or counts the same hours twice.

Memory Technique

Who controlled added, who paid delivery, where is the Manager Forecasts record?

Reference Hint

Open-book path: tab Builder's Guide to Accounting, 2001 to Builder's Guide to Accounting, Job cost forecasts and field logistics cost records; verify the trade cost, production, or field-control rule before answering.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.