A subcontractor completed electrical work on January 10th but was not paid by the general contractor. The owner made final payment to the general contractor on February 20th. Under California prompt payment law, what is the latest date the general contractor must pay the subcontractor?

Correct Answer

C) February 27th

The general contractor must pay subcontractors within 7 days of receiving payment from the owner, so by February 27th.

Answer Options
A
March 1st
B
January 17th
C
February 27th
D
March 22nd

Why This Is the Correct Answer

California's prompt payment statute (Civil Code Section 8814 for private works) requires a general contractor to pay subcontractors within 7 days of receiving payment from the owner. The owner paid the GC on February 20th, so 7 days later is February 27th — the latest date the GC must pay the subcontractor.

Why the Other Options Are Wrong

Option A: March 1st

March 1st would be 9 days after February 20th — beyond the 7-day statutory window. No provision allows this extended timeline once the GC has been paid.

Option B: January 17th

January 17th is 7 days after the subcontractor completed work (January 10th), but the prompt payment clock for GC-to-sub payment starts when the GC RECEIVES payment from the owner — not when the sub completes work. The GC cannot pay the sub before being paid by the owner under the standard pay-when-paid framework.

Option D: March 22nd

March 22nd is 30 days after February 20th. While 30-day payment windows appear in other payment contexts (e.g., owner to GC), the GC-to-sub requirement is 7 days, not 30.

Memory Technique

The '7-day pass-through rule': money flows down the payment chain within 7 days. Owner pays GC → GC has 7 days to pay subs → subs have 7 days to pay their sub-subs. Think of it as a relay race where each leg must be completed within 7 days of receiving the baton.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.