A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
Correct Answer
B) The following Monday
Under California prompt payment laws, contractors must pay subcontractors within 7 days of receiving payment. Monday + 7 days = the following Monday.
Why This Is the Correct Answer
Under California prompt payment laws (Business and Professions Code Section 7108.5), contractors must pay subcontractors within 7 days of receiving progress payments from property owners. When the contractor receives $18,000 on Monday, the 7-day payment period begins immediately. Counting 7 days from Monday (including weekends) leads to the following Monday as the deadline for paying the $12,000 owed to subcontractors.
Why the Other Options Are Wrong
Option A: Friday
Friday would only be 4 days after receiving payment on Monday. This falls short of the required 7-day payment period mandated by California law, making it an insufficient timeframe for compliance with prompt payment requirements.
Option C: The following Tuesday
The following Tuesday would be 8 days after receiving payment on Monday. This exceeds the 7-day maximum payment period required by law, potentially subjecting the contractor to penalties and legal consequences for late payment to subcontractors.
Option D: Thursday
Thursday would only be 3 days after receiving payment on Monday. This is significantly less than the required 7-day payment period, making it an inadequate timeframe that would violate California's prompt payment laws.
Memory Technique
Remember 'Lucky 7 Days' - contractors have exactly 7 days to pay subs after receiving payment. Count every day including weekends: Monday to Monday is exactly 7 days.
More ca-contracts Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
A service and repair contract for $950 must include all of the following EXCEPT:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A public works contractor submits a final payment application for $85,000. The public entity disputes $12,000 of the amount. Under prompt payment law, what amount must be paid within 30 days?
Next Question
A service and repair contract for $950 must include all of the following EXCEPT: