A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

Correct Answer

B) $12,000 - the undisputed amount

Under California law, the property owner must pay the undisputed portion ($15,000 - $3,000 = $12,000) within the required timeframe.

Answer Options
A
$0 - they can withhold payment until dispute is resolved
B
$12,000 - the undisputed amount
C
$3,000 - only the undisputed amount
D
$15,000 - the full amount

Why This Is the Correct Answer

Under California's prompt payment laws, property owners cannot withhold the entire payment when only a portion is disputed. They must pay the undisputed amount within the required timeframe to avoid penalties. In this case, $15,000 total minus $3,000 disputed equals $12,000 that must be paid promptly. The disputed portion can be withheld pending resolution, but the undisputed work must be compensated according to statutory requirements.

Why the Other Options Are Wrong

Option A: $0 - they can withhold payment until dispute is resolved

This is incorrect because California law prohibits withholding the entire payment when only a portion is disputed. Property owners must pay the undisputed amount within the required timeframe or face penalties, even while disputes are being resolved.

Option C: $3,000 - only the undisputed amount

This confuses the disputed amount ($3,000) with the undisputed amount. The undisputed amount is the total work completed ($15,000) minus the disputed portion ($3,000), which equals $12,000 that must be paid promptly.

Option D: $15,000 - the full amount

While the contractor performed $15,000 worth of work, the owner has legitimately disputed $3,000. California law allows withholding of disputed amounts pending resolution, so the full amount is not required immediately.

Memory Technique

Remember 'Pay the CLEAR, Hold the UNCLEAR' - pay the undisputed (clear) portion promptly, hold only the disputed (unclear) amount.

Was this explanation helpful?

More ca-contracts Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A service and repair contract for $950 must include all of the following EXCEPT:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.