A homeowner receives a door-to-door sales pitch and signs a $3,200 patio cover contract at 7 PM on Tuesday. When does the 3-day cancellation period expire?

Correct Answer

B) Friday at 11:59 PM

For contracts signed at the consumer's home, the 3-day period includes weekends. Tuesday evening to Friday midnight provides the full three days (Wed, Thu, Fri).

Answer Options
A
Saturday at 11:59 PM
B
Friday at 11:59 PM
C
Friday at 7 PM
D
Saturday at 7 PM

Why This Is the Correct Answer

Under California's Home Solicitation Sales Act (Civil Code §1689.5 et seq.), a consumer has 3 business days to cancel a home solicitation contract. The cancellation period runs through midnight of the third business day. Signed Tuesday evening, the three business days are Wednesday, Thursday, and Friday — expiring at midnight (11:59 PM) on Friday. Weekends and holidays do not count as business days, but in this case, all three days fall on weekdays.

Why the Other Options Are Wrong

Option A: Saturday at 11:59 PM

Saturday at 11:59 PM would apply if Saturday were counted as a business day, but the Home Solicitation Sales Act counts only business days (Monday–Friday). Wednesday, Thursday, and Friday are the three business days; Saturday is excluded.

Option C: Friday at 7 PM

Friday at 7 PM (the time the contract was signed, three days later) is a common intuitive answer, but legally incorrect. The cancellation period expires at midnight of the third business day, not at the same time the contract was signed. The law provides the full day — right up to 11:59 PM.

Option D: Saturday at 7 PM

Saturday at 7 PM incorrectly extends the period into Saturday (a non-business day) and uses the contract-signing time rather than midnight. Both elements are wrong — Saturday does not count as a business day and the deadline is midnight, not 7 PM.

Memory Technique

Think 'TWF' — Tue-Wed-Thu-Fri. Sign on Tuesday, cancel by Friday midnight. The 3 cancellation days are the three days AFTER signing: Wednesday (1), Thursday (2), Friday (3). Deadline = Friday at 11:59 PM. Weekends don't count, but here all 3 days are weekdays.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.