EstatePass
CaliforniaContractshard20% of exam part

A contractor agrees to install windows for $8,500. The homeowner provides the windows valued at $3,200. Under B&P 7159, what is the maximum allowable down payment?

Correct Answer

C) $1,000 plus the cost of materials

Under B&P 7159, the down payment can include $1,000 or 10% of contract price, whichever is greater, plus the cost of materials not delivered to the jobsite.

Answer Options
A
$850 (10% of total)
B
$1,000
C
$1,000 plus the cost of materials
D
$3,200 (cost of owner-provided materials)

Why This Is the Correct Answer

Under B&P 7159, the maximum down payment is the greater of $1,000 or 10% of the contract price, plus the cost of special-order or custom materials not yet delivered to the jobsite. Here, 10% of $8,500 = $850, which is less than $1,000, so the base is $1,000. However, the owner-provided windows ($3,200) were supplied by the homeowner — not by the contractor — so they do not add to the contractor's down payment. The correct reading is that the contractor can collect $1,000 (the B&P 7159 base) plus the cost of any materials the contractor themselves needs to procure. The answer '$1,000 plus the cost of materials' reflects the full B&P 7159 formula for situations where the contractor is procuring materials not yet on-site.

Why the Other Options Are Wrong

Option A: $850 (10% of total)

$850 (10% of $8,500) is less than $1,000, so the $1,000 floor applies. B&P 7159 uses the greater of 10% or $1,000 as the base — 10% alone understates the permissible down payment when it falls below $1,000.

Option B: $1,000

$1,000 alone ignores the materials component of B&P 7159. The statute allows the contractor to collect the $1,000/$10% base plus the actual cost of materials not yet delivered. Stopping at $1,000 understates what the contractor may legitimately collect.

Option D: $3,200 (cost of owner-provided materials)

$3,200 (the owner-provided materials cost) alone does not represent the correct down payment formula. The homeowner supplied these windows directly — they do not flow through the contractor's B&P 7159 materials component. The contractor's down payment is governed by the $1,000/10% base plus contractor-procured materials not yet on site.

Memory Technique

B&P 7159 down payment = '1K or 10%, whichever is greater, PLUS materials not on site.' The materials add-on only applies to items the contractor is procuring that have not yet arrived at the jobsite.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.