A contractor is renovating a home built in 1965 and will disturb painted surfaces totaling 8 square feet. What lead-based paint requirement applies under Oregon regulations?
Correct Answer
C) Must follow RRP Rule requirements including certification
Oregon follows EPA RRP Rule requirements. Work disturbing more than 6 sq ft of painted surfaces in pre-1978 housing requires RRP certification and procedures.
Why This Is the Correct Answer
Under the EPA Renovation, Repair, and Painting (RRP) Rule, work that disturbs more than 6 square feet of painted surfaces in pre-1978 housing triggers RRP Rule requirements, including contractor certification and specific work practices. Since 8 square feet exceeds the 6 square foot threshold and the home was built in 1965 (before 1978), full RRP Rule compliance is required.
Why the Other Options Are Wrong
Option A: No special requirements since area is under 10 square feet
The claim that no special requirements apply because the area is under 10 square feet is incorrect. The RRP Rule threshold is 6 square feet for interior work, not 10. At 8 square feet, the threshold is already exceeded.
Option B: Must hire certified lead abatement contractor
Hiring a certified lead abatement contractor is not automatically required for renovation work. Lead abatement is a separate process for permanently removing lead hazards. RRP-certified renovators (not abatement contractors) handle renovation, repair, and painting work, and abatement is not required unless the scope involves permanent hazard elimination.
Option D: Must provide EPA lead pamphlet but no other requirements
Providing the EPA lead pamphlet alone is insufficient. While distributing the pamphlet is one RRP requirement, contractors must also be certified and follow specific work practice standards. Pamphlet distribution without certification and proper procedures does not satisfy the RRP Rule.
Memory Technique
Remember '6 is the fix' β once you disturb 6 or more square feet of painted surfaces in pre-1978 homes, the RRP Rule kicks in. Six square feet is roughly the size of a standard interior door panel.
More Oregon Questions
Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?
An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?
A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?
Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?
A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?
A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.
A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?
What is the minimum experience requirement for obtaining an Oregon CCB contractor license?
A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?
A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
According to Oregon construction lien law (ORS 87), a subcontractor must file a lien claim within how many days after the earlier of completion of work or cessation of labor?
Next Question
Under Oregon building codes, what is the minimum width required for emergency egress windows in basement bedrooms?