According to Oregon construction lien law (ORS 87), a subcontractor must file a lien claim within how many days after the earlier of completion of work or cessation of labor?
Correct Answer
D) 75 days
Under ORS 87, subcontractors must file lien claims within 75 days of work completion or cessation.
Why This Is the Correct Answer
Under ORS 87, subcontractors must file lien claims within 75 days of work completion or cessation.
More or-supplement Questions
Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?
An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?
A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?
Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?
A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?
A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.
A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?
What is the minimum experience requirement for obtaining an Oregon CCB contractor license?
A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?
A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under Oregon's lead-based paint regulations, renovation work that disturbs more than how many square feet of lead-based paint requires EPA RRP certification?
Next Question
A contractor is renovating a home built in 1965 and will disturb painted surfaces totaling 8 square feet. What lead-based paint requirement applies under Oregon regulations?
