Under Oregon building codes, what is the minimum width required for emergency egress windows in basement bedrooms?
Correct Answer
D) 20 inches
Oregon building code requires emergency egress windows to have a minimum clear width of 20 inches for basement bedrooms.
Why This Is the Correct Answer
The correct answer is D (20 inches). Oregon building code, consistent with the IRC, requires emergency escape and rescue openings (egress windows) to have a minimum clear width of 20 inches. This allows a person to escape or a rescuer to enter in an emergency.
Why the Other Options Are Wrong
Option A: 30 inches
30 inches is incorrect. While 30 inches of clear width would certainly allow egress, it exceeds the minimum requirement. The code sets 20 inches as the minimum clear width.
Option B: 24 inches
24 inches is incorrect. This is a common distractor β 24 inches appears in various building code contexts (e.g., crawl space access dimensions) but is not the minimum egress window width.
Option C: 36 inches
36 inches is incorrect. This width relates to door minimum widths for accessibility, not egress window minimum clear widths. Confusing window and door minimums is a common error.
Memory Technique
Think '20-24-5.7': 20 inches wide, 24 inches tall, 5.7 sq ft net clear area. For the width alone: '20 inches β barely wide enough for shoulders.' Associate 20 with the minimum because it is the narrowest of the three dimensions.
More Oregon Questions
Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?
An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?
A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?
Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?
A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?
A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.
A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?
What is the minimum experience requirement for obtaining an Oregon CCB contractor license?
A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?
A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor is renovating a home built in 1965 and will disturb painted surfaces totaling 8 square feet. What lead-based paint requirement applies under Oregon regulations?
Next Question
A homeowner claims defective work and files a complaint with the CCB. Under ORS 701, what is the maximum the CCB can award from the Construction Contractors Board bond?