An emergency drill found 6 communication problems, and 4 are corrected. How many remain open?
Correct Answer
D) 2 problems.
Six problems minus four corrected leaves two open problems.
Why This Is the Correct Answer
Six problems minus four corrected leaves two open problems.
Why the Other Options Are Wrong
Option A: 1 problem.
1 problem. is below the supported result for emergency response; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 2 corrected.
2 corrected. is not aligned with the supported result for emergency response; it has the wrong label or classification even if the number looks close.
Option C: 4 problems.
4 problems. is above the supported result for emergency response; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Tracking Emergency-Response takeoff: count the condition before counting the package.
Reference Hint
Study anchor (closed-book): memorize Emergency response from Cal/OSHA Title 8 Sections 3203 and 1509; CSLB Law and Business Study. / Title 8 Section 3203 hazard correction; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?