A scaffold plank is damaged and visibly split. What should happen before use?
Correct Answer
A) Remove it from service and replace it.
Damaged scaffold components should not be used until repaired or replaced with sound material.
Why This Is the Correct Answer
Damaged scaffold components should not be used until repaired or replaced with sound material.
Why the Other Options Are Wrong
Option B: Use it only at the lowest level.
Use it only at the lowest level. may relate to another site control, but it does not remove or guard the scaffold safety exposure being tested.
Option C: Scaffold planning.
Scaffold planning. may relate to another site control, but it does not remove or guard the scaffold safety exposure being tested.
Option D: Let lighter workers use it for short tasks near the stair tower.
Let lighter workers use it for short tasks near the stair tower. may relate to another site control, but it does not remove or guard the scaffold safety exposure being tested.
Memory Technique
Scaffold Safety lock for Checking Masonry: damaged is the harm, components is the guard.
Reference Hint
Study anchor (closed-book): memorize Scaffold safety from Cal/OSHA Title 8 Construction Safety Orders; CSLB Law and Business. / Title 8 scaffold safety requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?