A final payment has cleared the bank and the claimant is releasing rights for that payment. Which release matches cleared payment?
Correct Answer
D) Unconditional release.
An unconditional release fits payment that has actually been received or cleared for the covered amount.
Why This Is the Correct Answer
An unconditional release fits payment that has actually been received or cleared for the covered amount.
Why the Other Options Are Wrong
Option A: Release payment based only on the contractor's assurance where a final payment has cleared the bank and the claimant is releasing rights for that payment, without checking releases against the payment request.
Release payment based only on the contractor's assurance where a final payment has cleared the bank and the claimant is releasing rights for that payment, without checking releases against the payment request. puts the item in the wrong financial bucket, timing, base, or comparison for the financial classification.
Option B: Accept an informal payment memo where a final payment has cleared the bank and the claimant is releasing rights for that payment, instead of checking the release or certificate before relying on it.
Accept an informal payment memo where a final payment has cleared the bank and the claimant is releasing rights for that payment, instead of checking the release or certificate before relying on it. puts the item in the wrong financial bucket, timing, base, or comparison for the financial classification.
Option C: Wait until final closeout to review claimant or insurance paperwork where a final payment has cleared the bank and the claimant is releasing rights for that payment.
Wait until final closeout to review claimant or insurance paperwork where a final payment has cleared the bank and the claimant is releasing rights for that payment. puts the item in the wrong financial bucket, timing, base, or comparison for the financial classification.
Memory Technique
An unlabeled Closing Payment dollar tells the wrong story.
Reference Hint
Study anchor (closed-book): memorize cited employment duty from CSLB Law and Business Study Guide; California Civil Code mechanics. / California Civil Code unconditional waiver and release forms; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?