The required contractor bond is $25,000, but the bond on file is $18,750. What shortage exists?

Correct Answer

A) $6,250.

The face-amount gap is $25,000 − $18,750 = $6,250. The $18,750 choice is the amount on file; $43,750 adds instead of subtracting; $5,250 is not the difference. This arithmetic does not calculate a bond premium or establish that multiple separate bonds can be combined. Source: https://www.cslb.ca.gov/contractors/maintain_license/bond_information/bond_requirements.aspx

Answer Options
A
$6,250.
B
$5,250.
C
$18,750.
D
$43,750.

Why This Is the Correct Answer

The face-amount gap is $25,000 − $18,750 = $6,250. The $18,750 choice is the amount on file; $43,750 adds instead of subtracting; $5,250 is not the difference. This arithmetic does not calculate a bond premium or establish that multiple separate bonds can be combined. Source: https://www.cslb.ca.gov/contractors/maintain_license/bond_information/bond_requirements.aspx

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.