For a public-works project subject to DIR electronic certified payroll reporting, what is the minimum submission frequency when the awarding-body contract does not require more frequent submission?

Correct Answer

D) At least monthly.

Submit at least monthly; an awarding-body contract may require more frequent reporting. Source: https://www.dir.ca.gov/Public-Works/PublicWorksSB854FAQ.html

Answer Options
A
Only at final completion.
B
Only when a worker complains.
C
Every two years with license renewal.
D
At least monthly.

Why This Is the Correct Answer

Submit at least monthly; an awarding-body contract may require more frequent reporting. Source: https://www.dir.ca.gov/Public-Works/PublicWorksSB854FAQ.html

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.