Non-emergency hidden framing damage changes the scope and price of a California home improvement contract. What should happen before the extra repair work proceeds?

Correct Answer

B) Document the change and obtain a change order signed by both parties.

For this non-emergency home improvement change, document the added work and obtain the required signed change order before proceeding.

Answer Options
A
Add the price only to the final invoice.
B
Document the change and obtain a change order signed by both parties.
C
Proceed on an unsigned supplier quotation.
D
Treat discovery alone as owner approval.

Why This Is the Correct Answer

For this non-emergency home improvement change, document the added work and obtain the required signed change order before proceeding.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.