A change-order cost worksheet records 14 labor hours at $86 per hour and $430 in materials. What is the total cost backup before other charges?

Correct Answer

B) $1,634.

Cost backup is 14 × $86 + $430 = $1,634. This computes the stated costs only; it does not authorize work or establish a compliant contract price.

Answer Options
A
$1,204.
B
$1,634.
C
$1,720.
D
$2,064.

Why This Is the Correct Answer

Cost backup is 14 × $86 + $430 = $1,634. This computes the stated costs only; it does not authorize work or establish a compliant contract price.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.