Law & BusinessContractsmedium23% of exam part

A bid addendum changes the specified roofing membrane three days before bid day. What should the bidder do?

Correct Answer

C) Acknowledge the addendum and include the revised scope in the bid.

Issued addenda become part of the bidding and contract documents, so the bidder should acknowledge the addendum and price its scope.

Answer Options
A
Use the old membrane and hope to change it after award.
B
Assume the cheaper contract interpretation where a bid addendum changes the specified roofing membrane three days before bid day, and price the work without an issued addendum.
C
Acknowledge the addendum and include the revised scope in the bid.
D
Submit the bid without mentioning which membrane is priced, while keeping the revised roofing product out of the bid file.

Why This Is the Correct Answer

Issued addenda become part of the bidding and contract documents, so the bidder should acknowledge the addendum and price its scope.

Why the Other Options Are Wrong

Option A: Use the old membrane and hope to change it after award.

Use the old membrane and hope to change it after award. skips the written authority, scope, price, notice, or release control needed for bidding and addenda.

Option B: Assume the cheaper contract interpretation where a bid addendum changes the specified roofing membrane three days before bid day, and price the work without an issued addendum.

Assume the cheaper contract interpretation where a bid addendum changes the specified roofing membrane three days before bid day, and price the work without an issued addendum. skips the written authority, scope, price, notice, or release control needed for bidding and addenda.

Option D: Submit the bid without mentioning which membrane is priced, while keeping the revised roofing product out of the bid file.

Submit the bid without mentioning which membrane is priced, while keeping the revised roofing product out of the bid file. skips the written authority, scope, price, notice, or release control needed for bidding and addenda.

Memory Technique

Bidding And Addenda: added scope rides with the bid, not with memory after opening.

Reference Hint

Study anchor (closed-book): memorize Bidding and addenda from CSLB 2026 Law Book; California contracting practice / CSLB Law Book bidding and contract administration; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.