A customer paid $7,500 to an unlicensed person for work requiring a license. Under B&P §7031's disgorgement concept, what amount may the customer seek to recover?
Correct Answer
D) $7,500.
B&P §7031 allows recovery of compensation paid to an unlicensed contractor for work requiring a license.
Why This Is the Correct Answer
B&P §7031 allows recovery of compensation paid to an unlicensed contractor for work requiring a license.
More ca-law-business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A homeowner signs a $23,500 home improvement agreement for a shower replacement before work starts. Under the lesser-of-10-percent-or-$1,000 deposit cap, what maximum deposit may be requested?
Next Question
The owner changes the selected window model but the price stays the same. What document control is still needed?