A concrete crew wants to place slab concrete over soft, pumping soil because reinforcement is already set. What should happen before the pour proceeds?

Correct Answer

C) Correct and recompact the subgrade so the slab has proper support.

Soft or pumping subgrade should be corrected before placement so the concrete is supported as designed.

Answer Options
A
Place concrete immediately so the slab bridges the soft area, at the same scheduled time shown on the pour calendar.
B
Add extra water to the concrete so it fills the pumping soil.
C
Correct and recompact the subgrade so the slab has proper support.
D
Leave the rough condition in place where a concrete crew wants to place slab concrete over soft, pumping soil because reinforcement is already set, and conceal the issue without correcting the rough work.

Why This Is the Correct Answer

Soft or pumping subgrade should be corrected before placement so the concrete is supported as designed.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.