A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?

Correct Answer

B) 5.93 cubic yards.

12 inches = 1 foot. Volume = 80 × 2 × 1 = 160 cubic feet; 160 ÷ 27 = 5.925925… cubic yards, or approximately 5.93. Waste and ordering allowances are excluded.

Answer Options
A
4.44 cubic yards.
B
5.93 cubic yards.
C
8.89 cubic yards.
D
17.78 cubic yards.

Why This Is the Correct Answer

12 inches = 1 foot. Volume = 80 × 2 × 1 = 160 cubic feet; 160 ÷ 27 = 5.925925… cubic yards, or approximately 5.93. Waste and ordering allowances are excluded.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Class B Trade Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.