A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
Correct Answer
B) 1,492 watts.
Two horsepower multiplied by 746 watts per horsepower equals about 1,492 watts.
Why This Is the Correct Answer
Two horsepower multiplied by 746 watts per horsepower equals about 1,492 watts.
Why the Other Options Are Wrong
Option A: 746 watts.
746 watts. is below the supported result for mechanical and electrical coordination; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 2,238 watts.
2,238 watts. is above the supported result for mechanical and electrical coordination; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 3,000 watts.
3,000 watts. is above the supported result for mechanical and electrical coordination; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Mechanical And cart for Coordinating Equipment: horsepower first, multiplied second, whole units last.
Reference Hint
Study anchor (closed-book): memorize Mechanical and electrical coordination from 2025 California Mechanical Code and 2025 California Electrical Code. / Title 24 California Mechanical/Electrical Code equipment coordination; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
A concrete housekeeping pad is 6 feet by 4 feet by 6 inches thick. How many cubic feet of concrete are needed before waste?
