A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
Correct Answer
A) 6.67 cubic yards.
Convert 4 inches to one-third foot, calculate cubic feet, then divide by 27 cubic feet per cubic yard.
Why This Is the Correct Answer
Convert 4 inches to one-third foot, calculate cubic feet, then divide by 27 cubic feet per cubic yard.
More ca-trade-b Questions
A waterproofing membrane at a balcony turns up the wall, but fasteners for trim are planned through the low portion of the turn-up. What is the concern?
Nonmetallic cable passes through a bored hole near the edge of a stud. What is the field concern?
A sloped roof drains into a wall corner with no kickout flashing at the lower end. What failure is most likely?
A rated wall has unsealed pipe penetrations after rough trades are complete. What should be coordinated before cover?
Sound-control insulation in a multifamily party wall is missing in several stud bays before drywall. What should be done?
A circular saw is used after the lower guard stops returning over the blade. What should be done?
A sound-control batt is missing around a plumbing penetration in a rated corridor wall. What is the best field response?
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
During a rough plumbing walk, a cleanout for a long horizontal waste line is shown behind a fixed cabinet panel. What is the best correction?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A project has 930 square feet of wall area and needs primer plus one finish coat. If coverage is 310 square feet per gallon per coat, how many gallons are needed before attic stock?
Next Question
The specification calls for moisture-resistant wallboard, but the finish schedule lists standard board in the same bathroom. What should the contractor do before ordering?