A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
Correct Answer
A) 6.67 cubic yards.
Convert 4 inches to one-third foot, calculate cubic feet, then divide by 27 cubic feet per cubic yard.
Why This Is the Correct Answer
Convert 4 inches to one-third foot, calculate cubic feet, then divide by 27 cubic feet per cubic yard.
Why the Other Options Are Wrong
Option B: 10.00 cubic yards.
10.00 cubic yards. is above the supported result for concrete quantity calculation; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option C: 18.00 cubic yards.
18.00 cubic yards. is above the supported result for concrete quantity calculation; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 66.70 cubic yards.
66.70 cubic yards. is above the supported result for concrete quantity calculation; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Measure to convert, adjust for inches, then let Estimating Flatwork set the finish line.
Reference Hint
Study anchor (closed-book): memorize Concrete quantity calculation from 2025 California Building Code, California Code of Regulations Title 24 / Title 24 California Building Code concrete construction; quantity estimating practice; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
A concrete housekeeping pad is 6 feet by 4 feet by 6 inches thick. How many cubic feet of concrete are needed before waste?
People Also Study
Related Study Resources
Previous Question
A project has 930 square feet of wall area and needs primer plus one finish coat. If coverage is 310 square feet per gallon per coat, how many gallons are needed before attic stock?
Next Question
The specification calls for moisture-resistant wallboard, but the finish schedule lists standard board in the same bathroom. What should the contractor do before ordering?
