The specification calls for moisture-resistant wallboard, but the finish schedule lists standard board in the same bathroom. What should the contractor do before ordering?

Correct Answer

B) Request clarification before purchase.

Conflicts in contract documents should be clarified before purchase or installation, commonly through an RFI or documented clarification.

Answer Options
A
Order the cheaper board immediately.
B
Request clarification before purchase.
C
Let the supplier choose at delivery.
D
Install first and ask at final inspection.

Why This Is the Correct Answer

Conflicts in contract documents should be clarified before purchase or installation, commonly through an RFI or documented clarification.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.