When measuring functional obsolescence from a superadequacy under a REPRODUCTION cost basis, the deduction generally includes:
Correct Answer
C) The excess cost less contribution, adjusted for depreciation already taken
Why this is correct: Under a reproduction cost basis, the cost to duplicate the superadequate feature exactly is included. The deduction for functional obsolescence is the excess cost of that feature (the cost above what a standard, adequate feature would cost or above its contributory value), adjusted to avoid double-counting any physical depreciation already applied. Why the other choices are wrong: "Nothing further, since reproduction cost already includes everything" ignores the need to deduct the superadequacy penalty. "Only the item's maintenance contract" is incomplete; the main penalty is the excess construction cost. "The full original cost of the entire building" is excessive; only the superadequate portion is penalized. Exam tip: Reproduction cost includes superadequacies; you must deduct their excess cost. Replacement cost avoids this by designing a modern equivalent.
Why This Is the Correct Answer
Why this is correct: Under a reproduction cost basis, the cost to duplicate the superadequate feature exactly is included. The deduction for functional obsolescence is the excess cost of that feature (the cost above what a standard, adequate feature would cost or above its contributory value), adjusted to avoid double-counting any physical depreciation already applied. Why the other choices are wrong: "Nothing further, since reproduction cost already includes everything" ignores the need to deduct the superadequacy penalty. "Only the item's maintenance contract" is incomplete; the main penalty is the excess construction cost. "The full original cost of the entire building" is excessive; only the superadequate portion is penalized. Exam tip: Reproduction cost includes superadequacies; you must deduct their excess cost. Replacement cost avoids this by designing a modern equivalent.
More Cost Approach Questions
In a cost approach for a proposed building, the appropriate cost basis is generally:
A warehouse cost $210,000 to build when the cost index stood at 105. The index is now 210. Its indicated current cost is:
The age-life method expresses depreciation as:
Market extraction of depreciation is limited by the fact that it:
Functional obsolescence caused by a deficiency is measured as curable when:
Curable physical deterioration is measured at cost to cure because:
A 2,050 sq ft dwelling is priced at $178 per square foot with a $34,000 detached garage and $21,500 of site improvements. Cost new is:
A house has three bedrooms sharing one bathroom, and adding a second bath is economically justified. This is:
Direct costs in a construction budget include:
An appraiser writes that a 40-year-old house has an effective age of 10 but describes original wiring, original kitchen and a 25-year-old roof. The report's problem is:
People Also Study
Real Estate Market
13.6% of exam
Property Description
11.8% of exam
Land or Site Valuation
4.5% of exam
Sales Comparison Approach
16.4% of exam
Income Approach
8.2% of exam
Previous Question
A 2,050 sq ft dwelling is priced at $178 per square foot with a $34,000 detached garage and $21,500 of site improvements. Cost new is:
Next Question
A house with effective age 12 and total economic life 60 has cost new of $290,000 plus a site worth $85,000. Its cost-approach value is: