Entrepreneurial incentive is best supported by:
Correct Answer
A) Market evidence of what developers require to build
Entrepreneurial incentive is the market-supported anticipated reward for development risk and effort. Developer interviews, feasibility and project evidence may help. Actual realized profit can be evidence but is not automatically the expected market incentive; neither a universal percentage nor a building-department label independently establishes it.
Why This Is the Correct Answer
Option A is correct because entrepreneurial incentive is a market-supported anticipated reward for development risk and effort. Evidence of what developers require to build, such as developer interviews, feasibility studies and project data, measures that market expectation. Full economic cost includes market-supportable entrepreneurial profit along with direct and indirect costs.
Why the Other Options Are Wrong
Option B: The appraiser's customary percentage for all assignments
Option B relies on the appraiser's customary percentage for all assignments. A single habitual percentage is not market evidence and does not reflect differences in property type, risk or market conditions.
Option C: The actual profit the current owner realized
Option C relies on the actual profit the current owner realized. Realized profit can be one piece of evidence, but it is not automatically the incentive the market expects, since one project's result may be higher or lower than what developers typically require.
Option D: A figure published by the local building department
Option D relies on a figure published by the local building department. A building-department figure does not independently establish what developers in the market require as a reward for risk and effort.
Ask the market's developers
Incentive is what developers in the market need to take on a project. If the evidence does not come from that market requirement, it is weaker support.
How to use: Use this when choosing between market-based and habit-based sources for any cost approach input.
Exam Tip
Choices that rely on a fixed customary figure or an outside label rarely beat a choice grounded in market evidence for a cost approach input.
Common Mistakes to Avoid
- -Applying the same incentive percentage to every assignment
- -Treating one owner's realized profit as the market incentive
- -Leaving entrepreneurial incentive out of full cost new
Concept Deep Dive
Analysis
This question tests what evidence supports entrepreneurial incentive in the cost approach. Entrepreneurial incentive is the market-supported anticipated reward a developer requires for the risk and effort of a project. The best support therefore comes from market evidence of what developers require, not from habit, one owner's result or an agency label.
Background Knowledge
Entrepreneurial incentive, or entrepreneurial profit when realized, is part of the full cost to create an improvement in the cost approach. It compensates the developer for coordinating the project and bearing risk. Appraisers support it with market evidence such as developer surveys and comparable project analysis.
Real-World Application
Appraising a new subdivision home, an appraiser interviews local builders and reviews recent project budgets to learn the profit margin they require. That market evidence supports the entrepreneurial incentive added to direct and indirect costs.
More Cost Approach Questions
Why can equivalent-utility replacement cost be useful for an obsolete improvement?
An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?
Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?
What best supports a claimed loss from a bathroom-layout deficiency?
Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?
Which scenario most strongly supports giving the cost approach substantial weight?
A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?
A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?
A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?
An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?
People Also Study
Real Estate Market
13.6% of exam
Property Description
11.8% of exam
Land or Site Valuation
4.5% of exam
Sales Comparison Approach
16.4% of exam
Income Approach
8.2% of exam
Previous Question
Consistent current dwelling cost new is $318,750 for 2,550 sf. What cost per square foot results?
Next Question
The base unit cost for 4,000 sf of improvements is $150 per square foot, before a local cost multiplier of 1.10. After the multiplier, the cost covers all cost components. Total depreciation of the improvements is $99,000, and site value is $170,000. What value does the cost approach indicate?
