A dwelling construction subtotal is 2,400 sf×$145/sf. Separate garage and sitework subtotals are $28,000 and $14,000, and none overlap. What sum of these stated cost components results? No statement is made about whether a separately supported entrepreneurial incentive is embedded.
Correct Answer
D) $390,000
2400×145+28000+14000 = 390000. Common errors: reporting only the dwelling subtotal gives $348,000; leaving out the sitework subtotal gives $376,000; leaving out the garage subtotal gives $362,000.
Why This Is the Correct Answer
Option D is correct because 2,400 sf x $145/sf = $348,000 for the dwelling, and adding the $28,000 garage and $14,000 sitework gives $348,000 + $28,000 + $14,000 = $390,000. The components do not overlap, so each is included once.
Why the Other Options Are Wrong
Option A: $348,000
Option A, $348,000, reports only the dwelling subtotal (2,400 x $145). The $28,000 garage and $14,000 sitework must be added, giving $390,000.
Option B: $362,000
Option B, $362,000, leaves out the garage subtotal: $348,000 + $14,000 = $362,000. Adding the $28,000 garage gives $390,000.
Option C: $376,000
Option C, $376,000, leaves out the sitework subtotal: $348,000 + $28,000 = $376,000. Adding the $14,000 sitework gives $390,000.
List every line, add once
Write each cost component on its own line, check that none overlap, and add each one once.
How to use: Use this when a cost question lists several separate subtotals.
Exam Tip
Count the components named in the stem and make sure your total includes each one.
Common Mistakes to Avoid
- -Reporting only the main dwelling cost
- -Leaving out a separately stated garage or sitework cost
- -Adding a component that is already included in the unit rate
Concept Deep Dive
Analysis
This question tests adding stated cost components that do not overlap. The dwelling subtotal is area times unit cost, and the garage and sitework subtotals are added once each. The note about entrepreneurial incentive means the question asks only for the sum of the stated components.
Background Knowledge
Cost estimates often combine a square-foot cost for the main building with separate costs for garages, porches and sitework. The appraiser should account for all direct and indirect costs of constructing the improvements, and consider separately whether entrepreneurial incentive is included.
Real-World Application
An appraiser estimates a house at a per-square-foot rate from a cost service, then adds a detached garage and sitework such as grading and utility connections priced separately. The total gives the improvement cost before any incentive and depreciation analysis.
More Cost Approach Questions
Why can equivalent-utility replacement cost be useful for an obsolete improvement?
An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?
Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?
What best supports a claimed loss from a bathroom-layout deficiency?
Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?
Which scenario most strongly supports giving the cost approach substantial weight?
A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?
A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?
A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?
An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?
People Also Study
Real Estate Market
13.6% of exam
Property Description
11.8% of exam
Land or Site Valuation
4.5% of exam
Sales Comparison Approach
16.4% of exam
Income Approach
8.2% of exam
Previous Question
Why are many external influences not curable by a subject-property renovation?
Next Question
The historical cost of an improvement was $350,000, and an appropriate index multiplier for the same scope of work is 1.20. Total depreciation is 20% of the trended cost, and site value is $175,000. What is the total indicated value?
