You are calculating the concrete needed for a foundation footing that is 2 feet wide, 1 foot thick, and 120 feet long around the perimeter. How many cubic yards of concrete are required?

Correct Answer

A) 8.9 cubic yards

Volume = 2 ft × 1 ft × 120 ft = 240 cubic feet. Convert to cubic yards: 240 ÷ 27 = 8.89 cubic yards, rounded to 8.9 cubic yards.

Answer Options
A
8.9 cubic yards
B
10.2 cubic yards
C
12.4 cubic yards
D
15.6 cubic yards

Why This Is the Correct Answer

Volume = Width × Thickness × Length = 2 ft × 1 ft × 120 ft = 240 cubic feet. Convert to cubic yards by dividing by 27 (since 1 cubic yard = 3 ft × 3 ft × 3 ft = 27 cubic feet): 240 ÷ 27 = 8.888... ≈ 8.9 cubic yards. This is the standard concrete volume calculation method used in field and exam settings.

Why the Other Options Are Wrong

Option B: 10.2 cubic yards

10.2 cubic yards results from a calculation error — possibly using incorrect dimensions or a wrong conversion factor. Some candidates mistakenly add a waste factor before dividing, arriving at this inflated number.

Option C: 12.4 cubic yards

12.4 cubic yards is significantly over the correct answer. This error typically stems from using 22 as the cubic feet-to-yards divisor, or from doubling one dimension incorrectly when setting up the volume formula.

Option D: 15.6 cubic yards

15.6 cubic yards is the highest distractor and is far above the correct calculation. This might result from forgetting to convert cubic feet to cubic yards altogether and then applying an incorrect formula.

Memory Technique

Cubic yards: 3 feet per side, cubed = 3³ = 27. Always divide your cubic feet answer by 27. Write '÷27' on your scratch paper immediately after you get cubic feet.

Was this explanation helpful?

More Michigan Questions

A residential foundation wall in Michigan is 8 feet high with 2 feet above grade. The backfill exerts lateral pressure of 30 psf per foot of depth. What is the maximum lateral pressure at the bottom of the foundation wall?

A builder discovers that the electrical service entrance was installed without proper permits. According to Michigan law, what is the most appropriate next step?

What is the maximum allowable span for a 2x8 floor joist (Grade 2 Douglas Fir) at 16" O.C. with 40 psf live load and 10 psf dead load according to Michigan Building Code span tables?

According to Michigan Building Code, what is the maximum height of a wood-framed bearing wall using 2x4 studs with standard construction?

A homeowner requests to convert a bedroom into a bathroom on the second floor. What is the primary Michigan code concern the builder must address?

According to Michigan plumbing regulations, what is the minimum pipe size required for a water service line serving a single-family residence?

A contractor is building a basement foundation wall that is 8 feet high and will retain 6 feet of soil. What is the minimum wall thickness required by the Michigan Building Code for poured concrete?

A homeowner wants to install a gas fireplace in their living room. The contractor notices the existing gas line is 1/2 inch black iron pipe. For a 40,000 BTU fireplace with a 25-foot run, is this pipe size adequate according to Michigan gas code?

During a framing inspection, the building official notes that the contractor used 2x4 studs at 24 inches on center for an exterior wall. According to Michigan Building Code, what is the maximum wall height allowed for this configuration?

A contractor is installing a beam to support floor joists. The beam must carry a total load of 8,000 pounds over a 12-foot span. If the allowable fiber stress for the lumber grade is 1,200 psi, what is the minimum required section modulus?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.