Which entity conducts building inspections under the NC State Building Code?
Correct Answer
A) Local building departments with state oversight
Local building departments conduct inspections under NC State Building Code with oversight from the NC Department of Insurance.
Why This Is the Correct Answer
NC law places primary inspection authority with local building departments (county and municipal inspectors), with oversight authority vested in the NC Department of Insurance's Engineering and Building Codes Division. This dual-layer system ensures local execution with state-level consistency.
Why the Other Options Are Wrong
Option B: Federal building inspectors
Federal building inspectors do not conduct routine building inspections under state codes. Federal involvement is limited to federally funded or owned projects. NC building code enforcement is a state and local function.
Option C: Private inspection companies only
Private inspection companies may perform some specialized inspections but cannot serve as the primary code enforcement authority. Code inspections that carry legal force must come from government-authorized inspectors, not private firms acting alone.
Option D: NC Department of Insurance only
The NC Department of Insurance does not directly conduct all inspections β that would be impractical given the volume of construction statewide. The DOI provides oversight and sets standards; local departments do the day-to-day inspections.
Memory Technique
Local = Legs on the Ground. Local building departments walk the job sites. The NC DOI watches from above (oversight). Think of it as police (local) vs. police chief at state level (DOI).
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor completes work on March 15th and sends a preliminary notice on March 30th. Under NC lien law, what is the last day to file a mechanic's lien?
Next Question
Under North Carolina workers' compensation law, what is the waiting period before benefits begin for a temporary total disability claim?