Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

Correct Answer

B) $12,000

Under NC lien law, a lien can only be filed for the amount actually owed, which is $12,000, not the total value of work performed.

Answer Options
A
$35,000
B
$12,000
C
$23,000
D
$47,000

Why This Is the Correct Answer

Under NC lien law, a subcontractor's mechanic's lien is limited to the amount actually owed and unpaid by the party above them in the contracting chain — here, the general contractor still owes $12,000. The lien amount is not based on the total value of work performed or materials supplied, but on the outstanding balance.

Why the Other Options Are Wrong

Option A: $35,000

$35,000 is the total value of materials and labor the subcontractor provided, but NC law does not allow a lien for the full contract amount — only for the unpaid balance actually owed.

Option C: $23,000

$23,000 ($35,000 − $12,000) represents what has already been paid, not the lien-eligible amount. There is no legal basis for filing a lien for the portion that has been satisfied.

Option D: $47,000

$47,000 ($35,000 + $12,000) combines total work value with the unpaid balance, which is a nonsensical calculation with no basis in NC lien law.

Memory Technique

Think 'Lien = What's Left.' You can only lien for money still owed — the leftover unpaid balance, not your total invoice.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

What is the maximum project value for an Intermediate General Contractor in North Carolina?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.