A contractor completes work on March 15th and sends a preliminary notice on March 30th. Under NC lien law, what is the last day to file a mechanic's lien?

Correct Answer

D) July 13th

The lien filing deadline is 120 days from the last furnishing of labor/materials (March 15th), making July 13th the deadline, regardless of when the preliminary notice was sent.

Answer Options
A
July 28th
B
June 28th
C
June 13th
D
July 13th

Why This Is the Correct Answer

Under NC lien law, the mechanic's lien must be filed within 120 days from the last furnishing of labor or materials. The clock starts on March 15th (last day of work), and 120 days later lands on July 13th. The preliminary notice date is irrelevant to this deadline.

Why the Other Options Are Wrong

Option A: July 28th

July 28th is incorrect. It appears to add 120 days from the preliminary notice date (March 30th), but the filing deadline runs from the last furnishing of labor/materials (March 15th), not from notice.

Option B: June 28th

June 28th is incorrect. It may represent approximately 90 days from March 30th (the notice date), but neither the 90-day period nor the notice date governs the lien filing deadline.

Option C: June 13th

June 13th is incorrect. It represents 90 days from March 15th (last work date), but NC law allows 120 days from last furnishing β€” not 90.

Memory Technique

NC = '1-2-0' β†’ 120 days from LAST WORK, not last notice. Think: 'NC lien = 4 months from final hammer swing.'

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.