EstatePass
North CarolinaNC Supplementhard100% of exam part

A contractor is performing a $45,000 residential addition. The homeowner has not paid the final $8,000. Under NC lien law, when must the preliminary notice be served?

Correct Answer

B) No preliminary notice required

For residential projects under $30,000, no preliminary notice is required under NC lien law. However, this project is $45,000, so preliminary notice should have been served before beginning work, but the question asks when it 'must' be served given the current situation.

Answer Options
A
Before beginning work
B
No preliminary notice required
C
Within 15 days of first furnishing labor
D
Within 30 days of contract signing

Why This Is the Correct Answer

Under North Carolina's lien statutes (N.C.G.S. Chapter 44A), a general contractor who directly contracts with the property owner (prime contractor) is NOT required to serve a preliminary lien notice to preserve lien rights. The preliminary notice requirement applies to first-tier and second-tier subcontractors and suppliers — not to the prime contractor. Since the contractor in this scenario has a direct contract with the homeowner, no preliminary notice is required regardless of the project value.

Why the Other Options Are Wrong

Option A: Before beginning work

'Before beginning work' is the timing rule that applies to certain subcontractors and suppliers under NC law, not to the prime contractor. Applying this rule to a direct-contract general contractor conflates the notice requirements for different parties in the contracting chain.

Option C: Within 15 days of first furnishing labor

'Within 15 days of first furnishing labor' echoes a requirement from other states (notably California's 20-day preliminary notice rule) or certain subcontractor notice rules. NC does not impose a 15-day preliminary notice requirement on a prime contractor who contracts directly with the owner.

Option D: Within 30 days of contract signing

'Within 30 days of contract signing' does not correspond to any NC preliminary notice deadline. This distractor blends contract-signing milestones with lien notice timing, neither of which accurately reflects NC lien law for a prime contractor.

Memory Technique

NC prime contractor + direct owner contract = NO preliminary notice needed. Think: 'Direct deal, no notice required.' The preliminary notice in NC is a protection mechanism for subcontractors and suppliers who lack a direct contract with the owner — the prime contractor already has a direct contractual relationship and lien rights attach automatically.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.