Under ORS 87, if a prime contractor receives payment from the property owner but fails to pay subcontractors, the unpaid subcontractors can file a lien claim within how many days of learning about the nonpayment?

Correct Answer

C) 75 days

ORS 87 allows subcontractors 75 days from completion of work or learning of nonpayment to file lien claims.

Answer Options
A
30 days
B
90 days
C
75 days
D
60 days

Why This Is the Correct Answer

75 days is correct. ORS 87 provides subcontractors a 75-day window to file lien claims after completing their work or learning of nonpayment by the prime contractor. This 75-day period is a core deadline in Oregon's construction lien statutes and applies consistently to subcontractors seeking to protect their right to payment.

Why the Other Options Are Wrong

Option A: 30 days

30 days is incorrect. 30 days is too short and does not match ORS 87's subcontractor lien deadline. A 30-day window is used in some preliminary notice requirements but not for filing the actual lien claim.

Option B: 90 days

90 days is incorrect. While 90 days is a common lien deadline in other states, Oregon's ORS 87 sets the subcontractor lien filing period at 75 days, not 90. Choosing 90 days reflects knowledge that the deadline is substantial but misses the specific Oregon figure.

Option D: 60 days

60 days is incorrect. 60 days is shorter than the actual 75-day period. Some candidates guess 60 days because it is a common administrative deadline, but ORS 87 specifically provides 75 days for subcontractor liens.

Memory Technique

In Oregon, the key ORS 87 lien number is 75 β€” across the board. Prime contractors: 75 days from completion. Material suppliers: 75 days from completion. Subcontractors: 75 days from completion or learning of nonpayment. '75 is the Oregon lien lifeline.'

Was this explanation helpful?

More Oregon Questions

Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?

An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?

A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?

Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?

A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?

A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.

A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?

What is the minimum experience requirement for obtaining an Oregon CCB contractor license?

A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?

A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.