A contractor is renovating a daycare center built in 1965. Special lead-safe work practices are required because the building was built before 1978 and is a:
Correct Answer
A) Child-occupied facility
EPA RRP rules apply to child-occupied facilities (where children under 6 regularly spend time) built before 1978, requiring certified renovators and lead-safe work practices.
Why This Is the Correct Answer
The EPA's Renovation, Repair, and Painting (RRP) Rule applies to target housing and child-occupied facilities built before 1978. A daycare center is classified as a 'child-occupied facility' because children under age 6 regularly spend time there. This classification triggers requirements for EPA-certified renovators and lead-safe work practices regardless of whether the building is residential.
Why the Other Options Are Wrong
Option B: Public building
Public building is not an EPA RRP regulatory category. The RRP Rule does not classify buildings simply as 'public' β the trigger categories are target housing (pre-1978 residential) and child-occupied facilities.
Option C: Commercial building
Commercial building is a general term, not the EPA RRP trigger category. A daycare operating in a commercial building is still subject to RRP requirements because children under 6 occupy it β making it a child-occupied facility.
Option D: Educational facility
Educational facility is too broad and is not the specific EPA RRP term. A high school, for example, is an educational facility but would not be a child-occupied facility under RRP since students are generally over age 6. The correct term is 'child-occupied facility.'
Memory Technique
RRP = Renovate where kids are Regularly Present (under age 6). 'Child-occupied' = children under 6 regularly spend time there. Daycare = children under 6 = child-occupied facility.
More Oregon Questions
Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?
An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?
A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?
Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?
A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?
A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.
A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?
What is the minimum experience requirement for obtaining an Oregon CCB contractor license?
A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?
A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under ORS 87, if a prime contractor receives payment from the property owner but fails to pay subcontractors, the unpaid subcontractors can file a lien claim within how many days of learning about the nonpayment?
Next Question
According to the Oregon Residential Specialty Code, what is the maximum allowable slope for a residential driveway?