Under Arizona lien law, if a property owner records a notice of completion on August 1st, by what date must subcontractors file their mechanics liens?
Correct Answer
B) September 30th
Subcontractors have 60 days from the recording of notice of completion to file mechanics liens. 60 days from August 1st is September 30th.
Why This Is the Correct Answer
Arizona lien law gives subcontractors 60 days from the recording of the notice of completion to file a mechanics lien. Counting 60 days forward from August 1st lands on September 30th (August has 31 days: 31 - 1 = 30 days remaining in August plus 30 days into September = 60 days total). September 30th is therefore the correct deadline.
Why the Other Options Are Wrong
Option A: October 1st
October 1st is 61 days from August 1st, one day past the deadline. The 60-day period expires on September 30th, not October 1st. This is a common off-by-one error when counting deadline days.
Option C: August 31st
August 31st is only 30 days from August 1st β half the required 60-day window. This would incorrectly cut the filing period in half and deprive subcontractors of their full statutory time to prepare and file a lien claim.
Option D: October 31st
October 31st represents 91 days from August 1st, which exceeds the statutory 60-day limit by over a month. This might reflect confusion with a 90-day period that applies in other lien contexts or other states.
Memory Technique
Use the '30+30=60' shortcut: from August 1st, you use up 30 days to reach August 31st, then 30 more days to reach September 30th β exactly 60 days. The deadline is the last day of September.
More Arizona Questions
What is the current minimum bond amount required for a residential contractor license in Arizona?
A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?
Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?
Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?
A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?
A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?
According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?
A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?
A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?
A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A residential contractor in Arizona completed work valued at $85,000 on March 15th. The property owner has not paid the final invoice of $12,000. What is the deadline for the contractor to record a preliminary 20-day notice under A.R.S. 33-981?
Next Question
A contractor completes work valued at $45,000 on a residential property in Arizona. The homeowner refuses to pay the final $12,000. How many days does the contractor have to file a preliminary notice to preserve lien rights under A.R.S. 33-981?