A contractor completes work valued at $45,000 on a residential property in Arizona. The homeowner refuses to pay the final $12,000. How many days does the contractor have to file a preliminary notice to preserve lien rights under A.R.S. 33-981?
Correct Answer
B) 20 days from commencement of work
Under A.R.S. 33-981, contractors must file a preliminary notice within 20 days of commencing work to preserve their lien rights.
Why This Is the Correct Answer
Under A.R.S. 33-981, a contractor (original contractor) must serve a preliminary 20-day notice within 20 days of first furnishing labor or materials to the project. This is the statutory deadline that preserves the right to later record a mechanic's lien if payment is refused.
Why the Other Options Are Wrong
Option A: 60 days from commencement of work
60 days is not the correct timeframe under A.R.S. 33-981. Confusing this with other notice periods (e.g., the 60-day window after project completion to record the lien itself) is a common error. The preliminary notice must be served much earlier β within 20 days of commencing work.
Option C: No preliminary notice required for contractors
This is incorrect and dangerous to assume. Original contractors do require a preliminary notice under A.R.S. 33-981 to preserve lien rights. Skipping this step forfeits lien protection entirely, leaving the contractor with only contract remedies.
Option D: 30 days from commencement of work
30 days is not the statutory deadline set by A.R.S. 33-981. This figure has no basis in Arizona's preliminary notice requirements and may be confused with other construction-law deadlines in other states.
Memory Technique
Think '20-day = 20-day notice' β the number matches the name of the notice. If you start work today, you have exactly 20 days to serve the preliminary 20-day notice or your lien rights vanish.
More Arizona Questions
What is the current minimum bond amount required for a residential contractor license in Arizona?
A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?
Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?
Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?
A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?
A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?
According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?
A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?
A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?
A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under Arizona lien law, if a property owner records a notice of completion on August 1st, by what date must subcontractors file their mechanics liens?
Next Question
An Arizona residential contractor receives a Notice of Claim against their bond. How many days do they have to respond to the ROC?