A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

Correct Answer

C) 60 days

Under Arizona lien law, a contractor has 60 days after recording of notice of completion to file a mechanics lien.

Answer Options
A
120 days
B
30 days
C
60 days
D
90 days

Why This Is the Correct Answer

Under Arizona Revised Statutes §33-992, a contractor has exactly 60 days after the recording of a notice of completion to file a mechanics lien. This timeframe is specifically designed to balance the contractor's right to secure payment with the property owner's need for certainty about potential liens. The 60-day period begins when the notice of completion is officially recorded with the county recorder, not when the work is completed or when payment disputes arise.

Why the Other Options Are Wrong

Option A: 120 days

120 days is the timeframe for filing a mechanics lien when no notice of completion has been recorded. This longer period applies when the project concludes without formal completion documentation, but once a notice of completion is recorded, the shorter 60-day deadline takes precedence under Arizona law.

Option B: 30 days

30 days is too short and does not align with Arizona mechanics lien statutes. This timeframe might be confused with other construction-related deadlines, such as certain notice requirements, but it is not the correct period for filing a mechanics lien after notice of completion.

Option D: 90 days

90 days is not the correct timeframe under Arizona law for filing a mechanics lien after notice of completion. This period might be confused with other states' requirements or different types of construction claims, but Arizona specifically requires action within 60 days of the recorded notice of completion.

Memory Technique

Remember 'Sixty days to Secure' - when a notice of completion is recorded, you have exactly 60 days to file your mechanics lien in Arizona. Think of it as two months to take action.

Was this explanation helpful?

More az-supplement Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

According to Arizona Revised Statutes, what is the minimum experience requirement for obtaining a residential contractor's license?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.