EstatePass
az-supplementArizona Business & Lawmedium

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Correct Answer

D) Yes, because it was filed within 20 days of commencement

Under Arizona lien law, the preliminary notice must be served within 20 days of first furnishing labor or materials. Since work began January 10th and notice was served January 18th (8 days later), it meets the requirement.

Answer Options
A
No, because it was not served on the owner within 20 days of commencement
B
Yes, because the notice was filed before delivery to the owner
C
No, because work had already commenced before filing
D
Yes, because it was filed within 20 days of commencement

Why This Is the Correct Answer

Under A.R.S. 33-981, the preliminary 20-day notice must be served within 20 days of first furnishing labor or materials to be valid for lien purposes. Work began January 10th and the notice was delivered to the owner on January 18th, which is only 8 days after commencement. Since 8 days is well within the 20-day requirement, the notice is valid. The timing of filing versus delivery is irrelevant as long as delivery occurs within the statutory timeframe.

Why the Other Options Are Wrong

Option A: No, because it was not served on the owner within 20 days of commencement

This is incorrect because the notice was served within 20 days of commencement. Work began January 10th and notice was delivered January 18th, which is only 8 days later, well within the required 20-day period under A.R.S. 33-981.

Option B: Yes, because the notice was filed before delivery to the owner

This is incorrect because the validity of the preliminary notice depends on when it's delivered to the owner, not when it's filed. The filing date is irrelevant to meeting the 20-day service requirement under Arizona lien law.

Option C: No, because work had already commenced before filing

This is incorrect because there's no requirement that the preliminary notice be filed before work commences. Arizona law only requires that the notice be served within 20 days of first furnishing labor or materials, regardless of when filing occurs.

Memory Technique

Remember '20 Days to Deliver' - the preliminary notice must be DELIVERED to the owner within 20 days of starting work, not just filed. Think 'Delivery Deadline = 20 Days'.

Was this explanation helpful?

More az-supplement Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

According to Arizona Revised Statutes, what is the minimum experience requirement for obtaining a residential contractor's license?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.