Calculate the maximum mechanics' lien amount a subcontractor can claim in Arizona if they were contracted for $25,000, completed $22,000 worth of work, but the general contractor only paid $15,000.

Correct Answer

A) $7,000

The lien amount is limited to the amount earned but unpaid: $22,000 (work completed) minus $15,000 (amount paid) = $7,000.

Answer Options
A
$7,000
B
$10,000
C
$25,000
D
$22,000

Why This Is the Correct Answer

$7,000 is correct because Arizona mechanics' lien law limits a subcontractor's lien to the value of work actually performed minus payments already received. The subcontractor completed $22,000 in work and was paid $15,000, leaving $7,000 unpaid and lien-eligible. The original contract amount ($25,000) is irrelevant because the subcontractor did not complete the full scope.

Why the Other Options Are Wrong

Option B: $10,000

$10,000 is incorrect. It appears to be the total contract minus payments ($25,000 − $15,000), but this ignores that only $22,000 of work was actually performed. A lien can only be claimed for work completed, not for unperformed portions of the contract.

Option C: $25,000

$25,000 is the full contract price, not the lien amount. The subcontractor cannot lien for unfinished work. Mechanics' lien rights are tied to the value of labor and materials actually furnished, not the total contracted amount.

Option D: $22,000

$22,000 is the total value of work completed, but it does not account for the $15,000 already paid. A lien secures only the unpaid balance of completed work, not the gross value of all work performed.

Memory Technique

Use the formula: LIEN = EARNED − PAID. Earned = work completed ($22,000). Paid = money received ($15,000). $22,000 − $15,000 = $7,000. The lien is the gap between what you did and what you got.

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.