A residential contractor in Arizona completed work valued at $85,000 on March 15th. The property owner has not paid the final invoice of $12,000. What is the deadline for the contractor to record a preliminary 20-day notice under A.R.S. 33-981?
Correct Answer
B) The preliminary notice deadline has passed since work began
The preliminary 20-day notice must be served within 20 days after the claimant first furnishes labor or materials, not after completion of work.
Why This Is the Correct Answer
Under A.R.S. 33-981, the preliminary 20-day notice must be served within 20 days after the claimant first furnishes labor or materials to the project, not after completion. Since the contractor completed $85,000 worth of work on March 15th, they clearly began work much earlier. The 20-day deadline from the start of work has already passed, making it too late to file a preliminary notice.
Why the Other Options Are Wrong
Option A: April 4th (20 days after completion)
This incorrectly calculates the deadline from completion date. The preliminary notice deadline is based on when work first begins, not when it's completed. April 4th would only be relevant if the notice period started from completion.
Option C: April 14th (30 days after completion)
This uses an incorrect 30-day timeframe and calculates from completion date. Arizona law requires the preliminary notice within 20 days of first furnishing labor/materials, not 30 days from completion.
Option D: May 14th (60 days after completion)
This uses an incorrect 60-day timeframe and calculates from completion date. The preliminary notice has a much shorter 20-day deadline from when work first begins, not 60 days from completion.
Memory Technique
Remember 'First Work = First Notice' - the preliminary 20-day notice clock starts ticking from the very first day you provide labor or materials, not when you finish the job.
More az-supplement Questions
What is the current minimum bond amount required for a residential contractor license in Arizona?
A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?
Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?
Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?
A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?
A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?
According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?
A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?
A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?
A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor receives a Notice of Hearing from the ROC for alleged license violations. How many days does the contractor have to request a hearing?
Next Question
Under Arizona lien law, if a property owner records a notice of completion on August 1st, by what date must subcontractors file their mechanics liens?
