On a nonexempt private project, the owner has already recorded the notice of commencement. A subcontractor now begins furnishing, has not served its notice to owner, and later remains unpaid. Which listed sequence follows the stated start and the notice-before-claim process?
Correct Answer
C) Notice of commencement recorded, notice to owner served, claim of lien recorded, enforcement action filed
With the commencement notice already recorded, the subcontractor next serves a timely notice to owner before recording its claim, then files enforcement if needed. This is not the only legally possible overall order: a notice to owner can be served before furnishing. The separate statutory deadlines and conditions still apply. Source: https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0700-0799/0713/Sections/0713.06.html
Why This Is the Correct Answer
With the commencement notice already recorded, the subcontractor next serves a timely notice to owner before recording its claim, then files enforcement if needed. This is not the only legally possible overall order: a notice to owner can be served before furnishing. The separate statutory deadlines and conditions still apply. Source: https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0700-0799/0713/Sections/0713.06.html
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Business & Finance Questions
The Quincy surety asks for the current backlog list. Which administrative file should the office update?
An Oakland Park queue has 38 invoices. Initial review is complete for 27 approved invoices and 6 separate invoices placed on hold. How many have not yet received initial review?
The Delray Beach startup needs to establish this accounting process: payables approval routing. Which startup control is most relevant?
A Winter Garden company's vendor checklist requires tax identification documentation before routine subcontractor payments are set up. Which listed record meets that step?
The Weston office receives this customer-credit issue: owner has slow payment history. Which administrative record should support the decision?
Estimated cost for a Port Orange commercial job is $865,000 and the contractor applies a 18% markup on cost. What selling price should be quoted?
A claim of lien was recorded 14 months ago. No amended claim or enforcement action has been filed, and no exception extending the period applies. What should the compliance calendar flag?
A Stuart office has the same employee receive customer checks and post the receipts. Which listed correction directly separates custody from recording?
A Palm Springs review checks 111 of 144 records. Exactly 15 distinct reviewed records have one or more defects. How many reviewed records have no defect?
A Jensen Beach supplier account has an $85,000 limit, a $53,400 balance and a proposed $18,600 order. With no other usage, fees or restrictions, what unused credit remains after the order?
People Also Study
Related Study Resources
Previous Question
For a crime directly related to contracting or the ability to practice contracting, which outcome is covered by section 489.129(1)(b)?
Next Question
An otherwise eligible Division I recovery-fund claim arises from a general contractor’s August 2024 contract. Under the payment tier effective January 1, 2025, what is the statutory maximum for this claim?