A portion of the building can be used for its intended purpose with minor punch items remaining. Which AIA A201 milestone applies?

Correct Answer

D) Apply substantial completion process

A201 defines Substantial Completion around use for intended purpose.

Answer Options
A
Bid opening
B
Final payment
C
Owner financing
D
Apply substantial completion process

Why This Is the Correct Answer

A201 defines Substantial Completion around use for intended purpose.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.