The parties disagree over whether a detail requires stainless steel fasteners. Which AIA A201 role may issue the interpretation?

Correct Answer

B) Request architect interpretation

A201 gives the Architect authority for interpretations and decisions under the Contract Documents.

Answer Options
A
Supplier redesign of the contract
B
Request architect interpretation
C
Bidder withdrawal after opening
D
Owner lien release

Why This Is the Correct Answer

A201 gives the Architect authority for interpretations and decisions under the Contract Documents.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.